Claims assessment on the 1 billion euro Barwa City housing development in Doha, Qatar.

Project:
Barwa City will cover a 2.7 million square meter land in Musameer, just outside the heart of Doha. The development offers its home owners and investors 128 apartment buildings, 6000 flats, and 1024 studio units. The city will also include schools, a hospital, mosques, parks, shopping complexes, health facilities and other amenities. It will have its own district cooling system and total wireless internet coverage.
Services:
We were appointed by the main contractor to provided planning support to substantiate a claim against the employer following delays to the programme.
The original Clause 14 programme contained over 22,000 programmed activities, many of which held resource and cost data.
Our high end PC’s and dedicated SQL Server enabled a timely delay analysis including impacted Clause 14 and Time Slice Preparation for the Planning Expert.